SEQUENCE OF OPERATION
On call for heat, the PC board will go through its safety chain (water pressure switch, high limit 1 & 2, roll-out,
etc.). When the safety chain is closed, the IID pilot will begin to spark and the pilot gas valve will open. A flame
will be lit at the pilot assembly. When an acceptable signal is sent back to the PC board, proving the rectifica-
tion, the D-2 Power Vent blower will start. When the blower comes up to speed, a draft proving switch will close
to allow the main gas valve on the heater to open. Note: On Low NOx units, the main gas valve & combustion
blower will turn on simultaneously. A heater with a D-2 Power Vent will continue to operate until call for heat is
satisfied.
DRAFT-PROVING SWITCH
The draft-proving switch ensures that the blower is operating. Once the D-2 Power Vent is wired to the heater,
the switch does not allow the PC board to open the main gas valve, unless it is closed.